Project: Design, construction and implementation of quick lime stone storage improvement system of Sarcheshmeh Copper Plant
- Client: National Iranian Copper Industries Company
- Duration: 36 months (2012)
- Necessity of implementation: Design and engineering, supply, construction, installation, testing and commissioning of quick lime stone storage improvement system, which is done to manage lime purchased from sources outside Sarcheshmeh copper plant. The project includes the construction of a 350-ton hopper and all material transfer systems to deliver the quick lime stored in the hopper to the final consumer. Thus, the maximum capacity of receiving and transporting quick lime in the plant has increased by 100 tons per hour.